> What an ADU needs from your electric panel, meter, water line, sewer and gas, and what California law says about fees and sprinklers. CSLB #1045801.

AI concept · not our work
1. [Home](https://dollhouseconstruction.com/)
2. [Guides](https://dollhouseconstruction.com/blog/)
3. ADU utilities

Guide · Last reviewed November 2026

# ADU utilities: panel, sewer, water, meters

The part of an ADU nobody shows in the renderings. What the unit needs from your electric service, water line, sewer and gas, and who decides each one.

[Check my lot for an ADU](https://dollhouseconstruction.com/free-estimate/)

[Call Dallas: (626) 991-8219](tel:+16269918219)

- CSLB #1045801
- 4.6 from 19 Google reviews
- Dallas answers the phone

By Dollhouse Construction Inc. · Published November 13, 2026 · Sources read November 13, 2026

A rendering of an ADU shows a kitchen, a bed and a window. It does not show the trench, the meter or the sewer cleanout, and those are often what decide the schedule and the budget. The unit needs power, water, a way to drain, and maybe gas, and each one has its own rules and its own agency.

## The short answer

Every ADU needs power, water and a sewer connection. The open questions are how big a service the main house can share, whether the unit gets its own meter, where the sewer line can run, and whether you bring gas at all. The answers come from three places: state law, your city's building department, and the utility that serves your address.

- **State law** limits what a city or utility can require for connections and fees, and it is more generous to units built inside existing space.**
- **Your city** decides the plan submittal: where the panel, meters and sewer go, and what the plumbing and electrical drawings must show.**
- **The utility** decides its own side: the meter spot, any service upgrade and the trench to its specification.**

## Electric: does the main panel have room?

You cannot answer this by looking at the panel door. The question is the total load on the service once the second home is added, and that is a calculation. San Dimas's 2025 ADU handout asks for it in plain terms:

- "Provide the main overcurrent size of the panel at the existing home."
- "Provide a load calculation for the front home (it must include the second home in the calculations) to justify the increased load for the 100A panel for the new dwelling unit." The handout adds that pool pump motors belong in the calculation if you have a pool.
- "The minimum size panel for the new residential unit is 100A."

The panel also touches the Energy Code. The CEC's ADU training deck says a new unit must be "energy storage systems ready" like any new single-family home. On the panel question, it says an ADU does not need its own 225-amp panel if its subpanel connects to the existing main panel, but only "if main panel has 225-amp busbar rating." (CEC 2022 Energy Code: ADU training deck)

Our [panel upgrade guide](https://dollhouseconstruction.com/blog/electrical-panel-upgrade-remodel/) covers the main-house side: what an upgrade involves, who pulls the permit and what gets inspected.

What this means for your project

Panel capacity, the sewer run and the meter question decide more of an ADU budget than the finishes do. Dallas checks them on the first visit.

[Call Dallas: (626) 991-8219](tel:+16269918219)

[Get my fixed-price quote](https://dollhouseconstruction.com/free-estimate/)

CSLB #1045801 · 4.6 from 19 Google reviews · Dallas answers the phone

## Subpanel off the house, or a separate meter?

There are two ways to power an ADU. A **subpanel** is fed from the main house's service, so the unit shares the house's meter and bill. A **separate service** is a second connection from the utility, with its own meter. Which one you can be made to use depends on the type of ADU.

### What state law says

HCD's handbook asks whether a local agency, special district or water corporation can require a new or separate connection. Its answer: ADUs created from existing space under Government Code 66323(a)(1) "cannot be required to install a new or separate connection unless the ADU or JADU is constructed concurrently with a new single-family dwelling." For all other ADUs, "a new or separate connection directly from the utility to the ADU or JADU may be required." (HCD ADU Handbook, March 2026, citing Gov. Code 66311.5(d) and (e))

So a garage conversion cannot be forced to get a second connection. A new detached ADU can be.

### What your city says

City pages do not always read the same way. West Covina's ADU page says ADUs "are not allowed to have second addresses or separate utilities," and its May 2025 guidelines say "No separate utility connection between the accessory dwelling unit/ junior accessory dwelling unit and the main dwelling." (City of West Covina) San Dimas's handout asks for the ADU's power source to be shown and for a new address, yours with the letter A added. (City of San Dimas)

We did not find a published rule that reconciles West Covina's wording with the state rule that a utility may require a separate connection for a new ADU. That is a question for the city and the utility, in writing, before the panel is designed. It is better to hear it before the trench than after.

### What SCE decides

SCE's Local Planning team handles the utility side. A city page that reproduces SCE's wording says: "Whether you are requesting to upgrade or install new electrical service, or require an electric meter set, everything you need to develop and complete your project is available through SCE's Local Planning department," and SCE encourages customers "to reach out to SCE early in your project." SCE's project request page lists "Accessory Dwelling Units" under new residential service, and puts a panel upgrade or a meter spot for an existing connection under existing service. (SCE; the City of Arcadia page is in Sources.)

## Water: one line or two

A shared water line is common when the city allows one, which makes sizing the main question. San Dimas's handout requires the plumbing plan to show "the point of interconnection to the water supply for the new dwelling unit," with pipe type and size, and then says:

- "A unit fixture calculation is required to justify the size of the water service, not only for the new ADU, but for the existing home as well. The common service line section must be sized to serve both dwellings."
- "The water heater is to be shown on the plans."
- The site plan must "show location of the main electrical panel, water and gas meter." (City of San Dimas)

Whether the ADU can have its own water meter is the same question as the electric one. HCD says the "new or separate connection" rule covers water corporations and special districts as well as the electric utility, so the answer depends on the unit type and on your water provider. The water purveyor also fills in part of the fire-flow sheet San Dimas requires, covered below.

Backflow prevention is not covered in the sources we read, so we are not saying what it requires. Ask your water provider and building department.

### The water heater

The Energy Code shapes this choice for a new detached ADU. The CEC's prescriptive path calls for a heat pump water heater (HPWH) in a new single-family dwelling located in a garage or conditioned space, and its training deck lists exceptions: a new dwelling unit of 500 square feet or less may use an "instantaneous electric water heater with point of use distribution," and a unit with one bedroom or less may use a 120-volt HPWH in place of a 240-volt one. For an ADU addition of 500 square feet or less, the CEC FAQ says "an instantaneous electric water heater may be used prescriptively." (CEC 2022 Energy Code FAQ and training deck, 2022 code; San Dimas lists the 2025 code, so confirm the edition.)

## Sewer: tie into the house, or a new line to the street

For a detached ADU, the sewer is often the longest and least visible run on the lot. San Dimas's handout gives the rule its building department uses:

- "The sanitary drainage system for the new ADU shall be connected to the building sewer of the main unit. New sanitary drainage systems are required to be separate and independent from any other building."
- The sewer line "is not allowed to connect to, pass through, or be installed under a dwelling unit, structure, garage, breezeway, patio cover, porch, steps or similar."
- The plumbing plan shows the pipe type and size, "a minimum of 2% slope," and "the location of the required cleanouts, including the building drain clean out within the first two feet of where the pipes exit the dwelling unit."
- It also shows "the size and location of the building sewer pipe where the system will be tied into." (City of San Dimas)

That last item is why it is worth asking about a camera inspection of the existing line before you commit to a layout. A tie-in only works if the line you are tying into is where you think it is, is sound, and is the right size. A new lateral to the street is a different project with a different agency, and we found no published rule in the sources we read on when one is required. Ask your city and your sewer provider.

## Gas: do you need it at all?

Nothing we read requires an ADU to have gas. If the unit has it, the plans must show it. San Dimas wants "a complete gas plan" showing "the point of connection to the gas service (location of the gas meter), the total gas piping system, and length of each section of pipe," with the BTU demand on each section. (City of San Dimas)

The Energy Code adds a second layer. The CEC says "newly constructed detached ADUs must meet the electric-ready requirements in Section 150.0(n)" when they use gas water heating, space heating, a cooktop or a dryer. The training deck lists what that means:

- For a gas water heater: a designated space for a future heat pump water heater, with a circuit and a reserved breaker in the main panel.
- For gas space heating, a gas cooktop or a gas dryer: a matching electric-ready circuit with a reserved and labeled double-pole breaker.

That is why an all-electric ADU is often simpler on paper: no gas line, no gas meter run and no ready circuits to reserve. It moves the weight to the electric side, where panel capacity and the heat pump choice matter more. Whether it suits you depends on how you cook, what the unit is for and what the load calculation says, so ask for both layouts before you decide.

## Fire sprinklers and solar

### Fire sprinklers

State law is direct. HCD: sprinklers can be required "only when sprinklers are required for the existing primary residence." It explains that "a detached single-family home designed and constructed decades ago would not have been required to have fire sprinklers," but if the main house "recently underwent significant alteration and is now required to have fire sprinklers, any ADU or JADU created after that alteration must be provided with fire sprinklers." And the ADU cannot be the reason the main house gets them: its construction "shall not trigger a requirement for fire sprinklers for the primary residence." (HCD ADU Handbook, citing Gov. Code 66314(d)(12) and 66323(d))

Sprinklers are not the only fire item. San Dimas requires an LA County Fire fire-flow, hydrant location and hydrant size sheet, with approvals "required prior to permit issuance" and parts filled in by the water purveyor and the building department. In a Fire Hazard Severity Zone the Wildland-Urban Interface code also applies, with a vegetation plan. (City of San Dimas)

### Solar on a new detached ADU

The CEC FAQ: "Newly constructed detached ADUs must have a newly installed solar PV to meet the prescriptive requirements." An existing system on the main house does not count. San Dimas says the panels can go on the ADU or on the main house, and the system can be a deferred submittal, but the plans must be approved before the framing inspection because "the wiring will need to be inside of the home (no external conduits)." Units built inside existing space or as additions are not subject to it. (CEC FAQ; City of San Dimas)

## Utility connection fees: what state law limits

We publish no fee amounts, and the agency serving your address sets them. Here is what the law says about when they can apply.

- **Existing-space ADUs.** HCD: these "shall not be considered by a local agency, special district, or water corporation to be a new residential use for purposes of calculating connection fees or capacity charges for utilities, unless constructed concurrently with a new single-family dwelling."**
- **Other ADUs.** The connection fee or capacity charge "shall be proportionate to the burden of the proposed ADU, based on its square footage or drainage fixture unit as compared to the primary dwelling." (HCD, citing Gov. Code 66311.5(e))**
- **Not an impact fee.** HCD's definition of "impact fee" "does not include any connection fee or capacity charge." The 750 square foot impact-fee exemption in our [ADU rules guide](https://dollhouseconstruction.com/blog/adu-rules-san-gabriel-valley/) does not remove a utility's connection charge.**

We tried the LA County Sanitation Districts connection fee page and it returned an access error, so we are not describing how that district handles ADUs. Ask your sewer provider for the current rule in writing.

## Before you call

1. **Find your main panel and its rating.** Photograph the label inside the door. We want the main breaker size.**
2. **Note overhead or underground service,** and where the SCE pole or underground box is.**
3. **Locate your water and gas meters** and the sewer cleanout, if you can find one.**
4. **Find your sewer line.** An old plot plan or past permits can show where it runs.**
5. **Note pool equipment, an EV charger or a planned heat pump,** because they feed the load calculation.**
6. **Ask your city in writing** whether the ADU may have its own meter or share the house's, and what plan check needs for the panel, sewer and fire-flow sheet.**

Dollhouse checks these on your lot first, and your written quote names the utility items that apply. To start, [ask for a lot check](https://dollhouseconstruction.com/free-estimate/) or call Dallas at [(626) 991-8219](tel:+16269918219).

## Questions we get

### Does my ADU need its own electric meter?

Not by state law alone. HCD says that for a new ADU, "a new or separate connection directly from the utility to the ADU or JADU may be required." For an ADU created inside existing space, it cannot be required. West Covina's guidelines say the opposite on the city side: "No separate utility connection between the accessory dwelling unit/ junior accessory dwelling unit and the main dwelling." Ask the city and SCE which applies to your lot.

### Can the city charge me sewer and water connection fees for an ADU?

For a unit built from existing space, HCD says a local agency, special district or water corporation cannot treat it as "a new residential use" when it calculates connection fees or capacity charges, unless it is built together with a new single-family home. For other ADUs, a connection fee or capacity charge "shall be proportionate to the burden of the proposed ADU," measured by square footage or drainage fixture units. The agency that serves your address sets the number.

### Does an ADU need fire sprinklers?

HCD: "Only when sprinklers are required for the existing primary residence." An ADU also cannot trigger a sprinkler requirement for the main house. The Wildland-Urban Interface code and LA County Fire's fire-flow sheet are separate items that can still apply.

### Do I have to run gas to an ADU?

No state rule in what we read requires it. If you do install gas water heating, a gas furnace, a cooktop or a dryer in a new detached ADU, the CEC says the unit "must meet the electric-ready requirements in Section 150.0(n)" and the related sections, which means reserved space and circuits for the electric version later.

### Will my main panel have to be replaced?

That depends on a load calculation, not a rule of thumb. San Dimas asks for the main overcurrent size at the existing home and a load calculation for the front home that "must include the second home." Your electrician and the utility decide what the result means for your service.

## Keep going

[See our ADU and garage conversion page](https://dollhouseconstruction.com/adu-construction/) · [Get a fixed-price quote](https://dollhouseconstruction.com/free-estimate/)

**More guides:** [ADU construction](https://dollhouseconstruction.com/adu-construction/) · [ADU rules in the San Gabriel Valley](https://dollhouseconstruction.com/blog/adu-rules-san-gabriel-valley/) · [Garage conversion or detached ADU](https://dollhouseconstruction.com/blog/garage-conversion-vs-detached-adu/) · [Electrical panel upgrade](https://dollhouseconstruction.com/blog/electrical-panel-upgrade-remodel/) · [San Dimas](https://dollhouseconstruction.com/service-area/san-dimas/) · [How we work](https://dollhouseconstruction.com/how-we-work/) · [Free estimate](https://dollhouseconstruction.com/free-estimate/)

**Note:** general background, not legal advice and not engineering advice. Utility rules change and differ by city and by provider. Confirm with your city's building department and your utilities before you design or buy anything.

## Sources

All pages opened and read November 13, 2026. Rules change. Confirm with your city before you rely on any of this.

Every source, with the date we read it

### State law and HCD

- HCD, Accessory Dwelling Unit Handbook, March 2026 (PDF; text extracted locally): [https://www.hcd.ca.gov/sites/default/files/docs/policy-and-research/ADU-Handbook-Update.pdf](https://www.hcd.ca.gov/sites/default/files/docs/policy-and-research/ADU-Handbook-Update.pdf) (read November 13, 2026)
- California Government Code section 66311.5 (utility connections and fees; text as published by FindLaw, since the official leginfo page blocks automated reads): [https://codes.findlaw.com/ca/government-code/gov-sect-66311-5/](https://codes.findlaw.com/ca/government-code/gov-sect-66311-5/) (read November 13, 2026)

### Energy code

- California Energy Commission, Energy Code Support Center, 2022 Energy Code FAQ (ADU questions on solar PV, water heating, electric-ready): [https://www.energy.ca.gov/programs-and-topics/programs/building-energy-efficiency-standards/energy-code-support-center-6/2022](https://www.energy.ca.gov/programs-and-topics/programs/building-energy-efficiency-standards/energy-code-support-center-6/2022) (read November 13, 2026)
- California Energy Commission, 2022 Energy Code: Accessory Dwelling Units training deck (PDF): [https://www.energy.ca.gov/sites/default/files/2025-07/2022_Energy_Code_Accessory_Dwelling_Units_ada.pdf](https://www.energy.ca.gov/sites/default/files/2025-07/2022_Energy_Code_Accessory_Dwelling_Units_ada.pdf) (read November 13, 2026)

### Southern California Edison

- SCE, Building, Renovation and Planning Project Requests: [https://www.sce.com/partners/consulting-services/building-renovations-planning-project-requests](https://www.sce.com/partners/consulting-services/building-renovations-planning-project-requests) (read November 13, 2026)
- SCE, Project Requests: [https://www.sce.com/partners/consulting-services/project-request](https://www.sce.com/partners/consulting-services/project-request) (read November 13, 2026)
- City of Arcadia, Requesting Power Service to Upgrade or New Service (SCE wording, PDF): [https://www.arcadiaca.gov/Document%20Center/Government/Development%20Services/Building%20Services/PSA%20City%20Website%20Language.pdf](https://www.arcadiaca.gov/Document%20Center/Government/Development%20Services/Building%20Services/PSA%20City%20Website%20Language.pdf) (read November 13, 2026)

### City pages

- City of San Dimas, ADU Requirements (2025) (PDF): [https://files.sandimasca.gov/Documents/Departments/Community%20Development/Building%20and%20Safety/Forms%20and%20Handouts/2025/ADU%20Requirements%2025%20FINAL.pdf](https://files.sandimasca.gov/Documents/Departments/Community%20Development/Building%20and%20Safety/Forms%20and%20Handouts/2025/ADU%20Requirements%2025%20FINAL.pdf) (read November 13, 2026)
- City of West Covina, Accessory Dwelling Units (ADU): [https://www.westcovina.gov/250/Accessory-Dwelling-Units-ADU](https://www.westcovina.gov/250/Accessory-Dwelling-Units-ADU) (read November 13, 2026)
- City of West Covina, ADU / JADU Guidelines, updated 05/2025 (PDF): [https://www.westcovina.gov/DocumentCenter/View/434](https://www.westcovina.gov/DocumentCenter/View/434) (read November 13, 2026)

Thinking about an ADU?

## Get a free estimate or call Dallas.

A free estimate starts with a conversation, and a written quote comes after someone has seen your panel, your meters and your yard.

(626) 991-8219
Talk to the owner
Link: tel:+16269918219

## Next step

- Free estimate: https://dollhouseconstruction.com/free-estimate/
- Call (626) 991-8219 (Dallas, the owner)
- All files for AI assistants: https://dollhouseconstruction.com/llms.txt