Do you need a permit to remodel a kitchen or bath in the San Gabriel Valley?

What seven nearby cities say, in their own words, with the pages we read.

  • CSLB #1045801
  • 4.6 from 19 Google reviews
  • Dallas answers the phone

By Dollhouse Construction Inc. · Published · City pages read November 5, 2026 · 9 min read

Yes, almost always. In the San Gabriel Valley cities we checked, almost every kitchen or bathroom remodel needs a permit. The trigger is the work, not the room. Moving or removing a wall, changing plumbing, adding or extending electrical circuits, or replacing drywall puts you in permit territory. Painting, new flooring, and swapping a faucet usually don't.

Cities word it differently. Claremont and San Dimas list cabinets as cosmetic work. Glendora's kitchen handout lists removing and replacing base cabinets and countertops as a permit trigger. Same valley, different rules, so read your own city's page.

Our contract lists the work, the materials, the payment schedule, our license number and who pulls the permits. Below: what each city says, and what happens if the permit is skipped.

AI-generated concept: a 1960s ranch house with a temporary fence, a permit holder on the fence, a dumpster and a pickup truck, foothills behindAI concept · not our work
A permit is posted at the job site.

San Dimas

Issues permits
Building and Safety Division, Community Development
Address
245 E Bonita Ave, San Dimas, CA 91773
Phone and hours
(909) 394-6200 main; (909) 394-6260 building manager line. Mon-Thu 7:30 am-5:30 pm, Fri 7:30 am-4:30 pm
Needs a permit
Remodeling that changes walls, windows or doors; electrical work such as panel upgrades or new or extended circuits; plumbing work and water heaters; window replacement. The city says its list "is not an all-inclusive list but should be used as a guideline only."
Exempt (city's wording)
Cosmetic projects such as painting, wallpapering, carpeting, cabinets and interior trim; plumbing repairs like washers and faucets; repairing fixtures on existing wiring; replacing switches and plugs
Plans
Plans required; type and detail "will vary based upon the scope of work." Three sets. Plans must follow the 2025 California Codes. HOA approval stamp needed before submittal if you have an HOA.
Inspections
Plumbing and/or electrical rough, framing, insulation, drywall, then plumbing, HVAC and electrical finals and a building final. Scheduled online. No separate charge per inspection (included in the permit cost, per the city).
Good to know
Work must start within one year of issue; pass an inspection at least every six months or the permit can expire. Design changes that affect exterior appearance need Planning approval.

San Dimas is where we are based. A cabinet swap alone is exempt here. Add a moved sink, a new circuit or a removed wall and it is not. More: Remodeling in San Dimas.

Glendora

Issues permits
Building Division (Building and Safety), Development Services
Address
116 E Foothill Blvd, Glendora, CA 91741
Phone and hours
(626) 914-8222 Building Division; (626) 914-8200 main. Mon-Fri 8:00 am-5:00 pm
Needs a permit
Kitchen: "removal & replacement and/or relocation of base cabinets, countertops, sinks, installed appliances, changes to the lighting, removal and replacement of any wallboard, modifications to the electrical, mechanical and plumbing systems." Bath: "removal & replacement and/or relocation of toilets, sinks, tub/showers, replacement/alteration to the electrical, or removal & replacement of gypsum board." (City handouts, 2025 editions)
Plans
Two sets: floor plan (existing, demo, proposed), electrical plan, framing details if walls move. The handout says engineering may be required if a demolished wall is load-bearing.
Inspections
Requested online by 4:00 pm the business day before; the city aims for next-day.
Online permits
Yes, through the Civic Access portal. City page: "Building permit applications are no longer accepted by email."
Good to know
The handouts cite Title 24 energy rules (high-efficacy lighting, bath vacancy sensor, IC/AT-rated recessed lights, range-hood airflow). The kitchen handout calls for a self-closing door between kitchen and garage. A submittal-requirements matrix for ADUs exists on the city site.

Glendora's kitchen handout lists replacing base cabinets or countertops as a permit trigger. Expect plans, not a counter permit, for most kitchens. More: Remodeling in Glendora.

La Verne

Issues permits
Building and Safety Divisions, Community Development (City Hall)
Address
3660 "D" Street, La Verne, CA 91750
Phone and hours
Building Department (909) 596-8706; City Hall (909) 596-8726. Building inspector office hours Mon-Thu 7:30-10 am, closed Fri. City Hall Mon-Thu 7:30 am-5:30 pm
Permit portal
The city lists a Building Permit Portal at laverne.geoviewer.io.

Call the Building Department before you start to find out what your project needs. More: Remodeling in La Verne.

Claremont

Issues permits
Building Division, Community Development
Address
City Hall, 207 Harvard Ave, Claremont, CA 91711
Phone and hours
(909) 399-5471 Building; (909) 399-5460 main. Permit issuance Mon-Thu 7:00 am-5:30 pm; counters Mon-Thu 7:00 am-6:00 pm
Needs a permit
City examples (not a complete list): water heater replacement, roof work, "addition of a new electrical circuit," construction of structures.
Exempt (city's wording)
"Projects that are cosmetic, such as painting, wallpapering, carpeting, cabinets and interior trim do not require a permit"; "repairing electrical fixtures on existing wiring, replacing switches, plugs and light ballasts."
Plans
Projects with plan sets are emailed to buildingapplications@claremontca.gov with the permit worksheet; permits without plans are issued over the counter. Check with Planning and Engineering first.
Inspections
Requested online. Have address, inspection type, permit number and phone ready.
Online permits
Yes: online form plus emailed plans. City note on the page, read November 5, 2026: "submittal responses are one week behind due to high volume of requests."

Claremont's wording matches San Dimas on cabinets. Build the city's one-week lag into any schedule. More: Remodeling in Claremont.

Covina

Issues permits
Building & Safety Division, Community Development
Address
125 E College St, Covina, CA 91723
Phone and hours
(626) 384-5460 Building (city handouts); City Hall (626) 384-5400. Mon-Thu 7:00 am-6:00 pm
Needs a permit
Handout #01 (effective January 1, 2026) lists "Remodels, alterations, and repairs," shower/tub enclosure replacements, water heater change-outs, and water, sewer or gas line work. "A plumbing, electrical, or mechanical permit may be required for any addition or changes to a building's existing system."
Exempt (city's wording)
Handout #09 (bath): "The replacement of the toilet, towel bars, mirrors, paint and floor coverings, where no other work is included is considered a maintenance item and no permit is required." Handout #01 also lists exterior painting and flatwork/landscape.
Plans
Remodels: four sets of plans plus two sets of other documents (such as Title 24 and structural calcs when required), on 18"x24" or 24"x36" paper. Bath minimum: dimensioned bath floor plan, whole-living-space floor plan, and a site plan.
Inspections
The city says inspections are required "through all phases of the construction project," requested by email with an approved permit.
Good to know
Title 24 energy forms "when required." Planning clearance first for exterior changes, added square footage and similar. Handout #09: smoke and CO alarms must be brought to current code for bath remodels over $1,000. Structural design and Title 24 documents must come from registered design professionals.

Covina asks for four sets of plans on a remodel. Allow design time before the permit. More: Remodeling in Covina.

West Covina

Issues permits
Building Division, Community Development (plan review by a city consultant; Fire Prevention reviews fire items)
Address
1444 W Garvey Ave S, Room 215, West Covina, CA 91790
Phone and hours
(626) 939-8425. Counter Mon-Thu 7:30 am-5:30 pm
Needs a permit
City FAQ: "Nearly any project to your home typically needs one." Electrical service upgrades need an electrical permit.
Exempt (city's wording)
Exemption bulletin (file dated September 28, 2022; the PDF was taken off the city site by November 2026, so ask the Building Division for the current list): "Painting, papering, tiling, carpeting, cabinets, counter tops and similar finish work where disabled access requirements do not apply." Also minor electrical repairs like replacing lamps, switches and receptacle devices. The bulletin warns: "Permits for plumbing, electrical, and/or mechanical work associated with exempt work above may be required."
Plans
FAQ (undated): small residential projects need 2 sets; larger ones 3 or more. Plan-check page: "Any work requiring a permit may not be started until the plans are approved and the permit is issued." Work started early is subject to a stop-work notice and non-compliance fee.
Inspections
Request through the Building Division, (626) 939-8425.
Online permits
Yes, through the One Stop Building Permit Center portal; email applications are no longer accepted (city page).
Good to know
Digital plan-review submittals only since June 1, 2023 (Fire plan-check page). West Covina and Covina are separate cities with separate offices. An ADU page exists on the city site.

West Covina says it plainly: nearly any home project needs a permit. The FAQ and bulletin are undated or old, so confirm before relying on them. More: Remodeling in West Covina.

Azusa

Issues permits
Building Division, Economic and Community Development Department
Address
213 E Foothill Blvd, Azusa, CA 91702
Phone
(626) 812-5234 plan review and permit tech; (626) 812-5223 inspection requests; (626) 812-5200 main
Needs a permit
City page: "A building permit is required whenever a structure or building is erected, constructed, enlarged, altered" (also repaired, moved, improved, converted or demolished).
Exempt (city's wording)
Includes "Painting, papering, and similar finish work." The city notes separate plumbing, electrical and mechanical permits may still be required for exempt items.
Plans
City document: interior work needing plan check is submitted by email as PDFs; plan review time "does not start until all required document are submitted and fees paid"; "A project valuation is required"; "Plans may be required."
Inspections
Request at (626) 812-5223; the owner, contractor or an employee must be present.
Good to know
Permit expires if work does not start within 180 days; one six-month extension on written request. Owner-builders must have owned the home for the last 12 months (city document).

Azusa's wording is broad: any alteration needs a permit unless it is on the exempt list. More: Remodeling in Azusa.

AI-generated concept: a 1970s kitchen mid-remodel with the wall opened, a header beam, a sub-panel and old galvanized pipe on the floorAI concept · not our work
An opened wall: this is what triggers a permit.

What happens if you skip the permit

Short version: the risk moves to you, and it shows up at the worst time.

  • Stop-work notices. Cities can stop work started before the permit is issued (West Covina plan-check page, read November 5, 2026).
  • Insurance. Ask your insurance agent how unpermitted work is treated on your policy.
  • CSLB rules. The Contractors State License Board says illegal contractors "can botch a job or leave with the down payment." It also says homeowners could be asked to pay for injuries if unlicensed or uninsured workers are hurt, and that unpaid suppliers can file mechanics liens (CSLB, read November 5, 2026). Sign a permit as an owner-builder and "you assume full responsibility for all phases of your project and its integrity" (CSLB wording as reproduced in Azusa's permit document).
  • Check any contractor. Look up the license at cslb.ca.gov. Ours is CSLB #1045801.

What this means for your project

We pull permits for the jobs we build, in every one of these cities. Tell Dallas your city and your scope and he can say what the permit will involve.

CSLB #1045801 · 4.6 from 19 Google reviews · Dallas answers the phone

Permits in a Dollhouse remodel

The contract lists the work, the materials, the payment schedule, our license number and who pulls the permits. See how we work for the full process, and what happens when a wall opens up.

Services: kitchen remodeling · bathroom remodeling.

Questions we get

Do I need a permit to replace kitchen cabinets only?

It depends on the city. Claremont and San Dimas list cabinets as cosmetic and exempt. Glendora lists removing and replacing base cabinets and countertops as needing a permit. If plumbing or electrical moves with them, a permit applies everywhere. Call your city first.

Do I need a permit to remodel a bathroom in Covina?

Usually yes. Covina's bath handout says a remodel generally needs a permit, including wall framing, sinks, tubs and showers, plumbing, electrical and drywall. Replacing a toilet, towel bars, mirrors, paint or floor coverings with no other work is called maintenance.

Who is allowed to pull the permit?

Covina's handout names a residential owner, a licensed California contractor, or an authorized agent. Azusa adds that owner-builders must have owned the home 12 months. If you pull it as owner-builder, you carry the project's responsibility.

How long does a permit take?

Cities do not publish one number for kitchens and baths. West Covina's FAQ gives about 14 working days for small additions. Claremont said on November 5, 2026 that responses were one week behind. Ask your city for its current turnaround.

How do I check a contractor is licensed?

Look up the license number at cslb.ca.gov. Ours is CSLB #1045801. Ask any contractor which permit the job needs and who pulls it. Be wary of anyone who suggests skipping the permit.

Note: rules change; confirm with your city before you start.

Sources

All pages opened and read November 5, 2026. Rules change. Confirm with the city before you start.

Every source, with the date we read it
Planning a kitchen or bath?

Get a free estimate or call Dallas.

A free estimate starts with a conversation. Ask about permits for your city and your project.

(626) 991-8219Talk to the owner

Get your free estimate

Two required fields. Dallas or his team will reach out to you directly. No pressure, no obligation.

CSLB #1045801 · We use your details to respond to your request. Unless your browser sends Global Privacy Control, a scrambled (hashed) version of your email or phone, plus your IP address and browser type, may go to Meta to measure our ads. Privacy and ad choices

Call nowFree estimate